Asbestos-Containing Material (ACM) Remediation & Disposal
- Client Sector: Industrial Sector
- Facility Type: Downstream Industrial Storage & Distribution Facility
- Volume Managed: 900 Cubic Meters Total Volume
- Execution Date: 2025
Compliance Standards: Local Environmental Mandates, Occupational Health & Safety (OSHA), and International Hazardous Material Disposal Protocols
Execution Summary
In 2025, Piranha successfully planned, containment-certified, and executed a large-scale Asbestos-Containing Material (ACM) management project for an industrial facility specializing in refined fuel products. Managing a total of 65 twenty-cubic-yard loads, Piranha provided turnkey hazardous waste containment, safe site logistics, transport, and compliant final disposal.
The project was completed on schedule with zero safety incidents, ensuring the structural integrity and operational safety of the refined fuels facility while strictly adhering to regulatory
guidelines.
Key Achievements & Operational Highlights
- Large-Scale Hazardous Containment: Safely loaded, sealed, and managed sixty-five (65) 20-cubic-yard roll-off bins/containers containing ACM, ensuring zero airborne fiber release during site operations.
- Industrial Site Integration: Coordinated logistics seamlessly within an active downstream refined fuel distribution environment without disrupting core operations or compromising facility fire and safety protocols.
- Rigorous HSE Protocols: Applied comprehensive decontamination processes, negative pressure containment (where applicable), personal protective equipment (PPE) enforcement, and continuous air monitoring throughout the abatement phase.
- Full Regulatory Compliance: Executed end-to-end chain-of-custody documentation, waste manifests, and final disposal in strict compliance with environmental protection authorities and hazardous material regulations.